business

Dec. 8, 2020

STAFF REPORTER

2 min read

LHWP construction picks momentum

LHWP construction picks momentum

Construction of the Polihali Weir

Metro Audio Articles

Catch our weekly audio news daily only on Metro Radio Podcast News.

listen now

CONSTRUCTION work at the Lesotho Highlands Water Project (LHWP) is in top gear despite a slow start in May due to the COVID-19 pandemic.

Excavations continue from the outlets at about six metres a day per tunnel at the Polihali diversion tunnels.

The water project is being supported by the Kingdom of Lesotho and the Republic of South Africa.

The Lesotho Highlands Development Authority (LHDA) Chief Executive Officer Tente Tente says excavation of the intake and outlet portals has been completed and work on the tunnels’ concrete lining is under way, with concrete casting and reinforcement having been started on tunnel one.

“Both tunnels’ intake and outlet portals drives have been supported with sprayed concrete and rock bolts and preparatory works for the concrete inlet structure also ongoing,” says Mr Tente.

The tunnels (one seven metres in diameter and almost 1km long; and the second, nine metres in diameter and also almost 1km long) run parallel to each other from the intake point to the outlet downstream of the dam.

The tunnels are being excavated in advance of the construction of the Polihali dam to reduce the dam construction period. Impoundment of the Polihali reservoir is expected to start in 2024, with water delivery planned to start in 2027.

The LHWP is a multi-phased, multi-billion maloti/rand project between the governments of Lesotho and the Republic of South Africa.

It comprises water transfer and hydropower generation components with associated ancillary developments.

The water transfer component entails the construction of dams and tunnels in Lesotho, enhancing the use of water from the Senqu (Orange) River and its tributaries by storing, regulating, diverting and controlling the flow to effect the delivery of specified quantities of water to South Africa, and utilising the delivery system to generate hydro-electric power in Lesotho.

Enjoy our daily newsletter from today

Access exclusive newsletters, along with previews of new media releases.

The major works of Phase I included the construction of the Katse Dam, the transfer and delivery tunnels, the ’Muela Hydropower Plant and the Mohale Dam.

The Phase II water transfer component comprises a dam at Polihali and a gravity tunnel that will connect the reservoir in Polihali with the Katse reservoir.

Further feasibility studies for the hydropower component of Phase II have concluded that conventional hydropower is the more feasible option to meet Lesotho’s energy needs.

The LHDA is the implementing and management authority of the LHWP on behalf of the Lesotho government.

CCE News

Share the story

METRO WEATHER FORECAST